ScottM5 (Colorado)
Posts: 3
Posts: 3
Posted:
I am a board member for a small (23-unit) condo complex in Colorado. Aside from issues of non-payment among owners, we are dealing with problems on a major repair project.
The 2007-2008 winter was hard on the buildings, leaving some exterior damage to already-aging buildings. In spring of 2008, our property manager contact the board and said our insurance company would drop our coverage unless we pursued repairs. With this pressure to get something under way immediately, we settled on a bid from a local contractor to do some general exterior repairs and repainting. While our insurance paid some money toward this end, we were forced to do a relatively large assessment with little notice that has caused lingering problems for a few owners.
While we have been struggling through collection issues, the contractor started work in the fall of 2008, but did not complete before winter set in. Along the way, he has added to the finalized bid of rough $90,000 at least another $30,000 for things he claims to have found and had to repair and replace. Unfortunately, the initial bid and subsequent changes exist as email exchanges rather than a written contract. Checks have been written to him, work has been sporatic, and I feel it's safe to say tempers are worn on both sides. He expresses constant complaints about the original construction and about the HOA dragging its heels on paying for his materials and extra work he's had to do. Owners complain that the work is still not looking close to finished after a year and half even with what's been paid thusfar and that some of the work looks sub-par or has not held up to weathering thusfar.
There now remains $14,000 outstanding on the "total amount owed." The board was under the impression, though not explicitly told, materials were covered by this point and the remaining amount could be paid upon completion (partly because we don't really have much else as leverage to get him to finish). Now he has asked for another $11,500 of that amount for more materials before he continues with work, going so far as to say if he did not receive payment at the end of the week he would postpone work on our buildings until fall and move on to other projects in the meantime.
This, of course, increases owner concerns about being taken for a ride. Is it unreasonable to expect a percentage on a project like this to be paid on completion as opposed to during work? Is there any recourse against this sort of treatment? Is there anything we can do to make sure the work is completed in a timely and satisfactory fashion?
Or, in short, does anyone have any advice? I'm about at wit's end.
The 2007-2008 winter was hard on the buildings, leaving some exterior damage to already-aging buildings. In spring of 2008, our property manager contact the board and said our insurance company would drop our coverage unless we pursued repairs. With this pressure to get something under way immediately, we settled on a bid from a local contractor to do some general exterior repairs and repainting. While our insurance paid some money toward this end, we were forced to do a relatively large assessment with little notice that has caused lingering problems for a few owners.
While we have been struggling through collection issues, the contractor started work in the fall of 2008, but did not complete before winter set in. Along the way, he has added to the finalized bid of rough $90,000 at least another $30,000 for things he claims to have found and had to repair and replace. Unfortunately, the initial bid and subsequent changes exist as email exchanges rather than a written contract. Checks have been written to him, work has been sporatic, and I feel it's safe to say tempers are worn on both sides. He expresses constant complaints about the original construction and about the HOA dragging its heels on paying for his materials and extra work he's had to do. Owners complain that the work is still not looking close to finished after a year and half even with what's been paid thusfar and that some of the work looks sub-par or has not held up to weathering thusfar.
There now remains $14,000 outstanding on the "total amount owed." The board was under the impression, though not explicitly told, materials were covered by this point and the remaining amount could be paid upon completion (partly because we don't really have much else as leverage to get him to finish). Now he has asked for another $11,500 of that amount for more materials before he continues with work, going so far as to say if he did not receive payment at the end of the week he would postpone work on our buildings until fall and move on to other projects in the meantime.
This, of course, increases owner concerns about being taken for a ride. Is it unreasonable to expect a percentage on a project like this to be paid on completion as opposed to during work? Is there any recourse against this sort of treatment? Is there anything we can do to make sure the work is completed in a timely and satisfactory fashion?
Or, in short, does anyone have any advice? I'm about at wit's end.