JavierG (Texas)
Posts: 4
Posts: 4
Posted:
We built a new house recently and before build, we submitted house plan submittals. Everything was approved but we now have the HOA board threatening to potentially sue us because our driveway is out of compliance. Our CCRs are over 20 years old and regarding driveways it says: "All driveways in the Subdivision must be constructed of reinforced concrete dowelled into existing curb, washed gravel finish, brick pavers or other materials as approved by the Architectural Committee." During the submittal process, the Architectural Committee asked, "Please provide a plot plan showing the proposed driveway and confirm that the driveway material will be in compliance with the KCPOA CCRs, attached.” Our builder responded that driveway material would be concrete and will be in compliance. They then asked for a plot plan to reflect the materials planned and the builder responded with a plat with the word "concrete" written on the driveway. A few days later, the ACC approved our plans as submitted and we proceeded with the build.
The house took 6 months to build and the day after our driveway is poured, the AC emails us and notifies us that our driveway is out of compliance and is supposed to have a washed aggregate finish. We let them know that was never our intention and never did they ask anything about finish prior to approval. They let us know that they could see no path forward and that they would close the file and said they would discourage owners to use our builder in the future.
Several weeks later the HOA Board let us know that due to complaint calls they have received on our driveway that we need to change our driveway to a washed aggregate finish. They were willing to make an exception since we already poured that we'd only have to pull out the beginning of our driveway-- about 50 feet (it's a very long driveway). This cost be out of our pocket.
The Board insists that the CCR requirement specifically states that driveways be concrete with a washed gravel finish. We don't read it that way and neither does our attorney that we've consulted. We've made them aware that the driveways could also be built with brick pavers or other material approved by the ACC. They also claim that because our builder stated our driveway would be concrete and comply with the restrictions that it gave the indication that we would be complying with the finish requirement. We think that is an assumption on their part because finish was NEVER brought up. They threatened us and said that if they have to pursue this as a legal matter that any past offers are null and void and will pursue removal and replacement of the entire driveway, with one that is compliance with the CCRs.
Our neighborhood has about 15-20 homes, very small. Some are fully washed aggregate, some are washed aggregate for the first 10-20 feet and then concrete and our neighbor has a fully laid concrete driveway. Our attorney has written the Board a letter saying that with the plain language of the CCRs and the course of communication with the ACC that we comply and that the ACC approved the concrete as laid.
I'm curious what opinions are. We feel the Board is reading into what the CCRs is saying and have expressed that they believe that it says, "concrete dowelled into the existing curb WITH A washed gravel finish", however that totally changes the meaning and is not what it says.
The house took 6 months to build and the day after our driveway is poured, the AC emails us and notifies us that our driveway is out of compliance and is supposed to have a washed aggregate finish. We let them know that was never our intention and never did they ask anything about finish prior to approval. They let us know that they could see no path forward and that they would close the file and said they would discourage owners to use our builder in the future.
Several weeks later the HOA Board let us know that due to complaint calls they have received on our driveway that we need to change our driveway to a washed aggregate finish. They were willing to make an exception since we already poured that we'd only have to pull out the beginning of our driveway-- about 50 feet (it's a very long driveway). This cost be out of our pocket.
The Board insists that the CCR requirement specifically states that driveways be concrete with a washed gravel finish. We don't read it that way and neither does our attorney that we've consulted. We've made them aware that the driveways could also be built with brick pavers or other material approved by the ACC. They also claim that because our builder stated our driveway would be concrete and comply with the restrictions that it gave the indication that we would be complying with the finish requirement. We think that is an assumption on their part because finish was NEVER brought up. They threatened us and said that if they have to pursue this as a legal matter that any past offers are null and void and will pursue removal and replacement of the entire driveway, with one that is compliance with the CCRs.
Our neighborhood has about 15-20 homes, very small. Some are fully washed aggregate, some are washed aggregate for the first 10-20 feet and then concrete and our neighbor has a fully laid concrete driveway. Our attorney has written the Board a letter saying that with the plain language of the CCRs and the course of communication with the ACC that we comply and that the ACC approved the concrete as laid.
I'm curious what opinions are. We feel the Board is reading into what the CCRs is saying and have expressed that they believe that it says, "concrete dowelled into the existing curb WITH A washed gravel finish", however that totally changes the meaning and is not what it says.